Project Integration Management Task 1 (Weighted Scoring Model)
Weighted Scoring Model for Manage Your Health Inc.Created by: Charles Barnes Date: 10/30/18 Criteria Weight % Project 1 Project 2 Project 3 Project 4
Runs on current Intranet 30% 90 90 50 20
Helps employees improve their health 10% 70 90 50 20
Saves company money 10% 50 90 50 20
Increase company profits 15% 25 90 50 70
Strong customer support 5% 20 20 50 90
Cost of development 20% 50 70 50 50
Implemented in under one year 10% 20 50 50 90
Weighted Project Scores 100% 55.75 78.5 50 44
-5000625635000
Project Integration Management Task 2 (Project Charter)
Project Charter
October 31st, 2018
Project Title: Recreation and Wellness Intranet Project
Project Start Date: October 30th, 2018 Projected Finish Date: April 30th, 2018
Budget Information: The company has budgeted $200,000 for this project. The majority of costs for this project will be for application development.

Project Manager: Charles Barnes, (253) 720-5649, [email protected]
Project Objectives: The Recreation and Wellness Intranet Project is an essential proejct for our organization. We will likely complete this task within six months for close to $200,000. By providing this application on our present Intranet, we can enable employees to enhance their wellbeing, therefore bringing down medicinal services costs and enhance productivity. The application will enable workers to enroll for organizational supported recreational programs, wellbeing related classes and programs, track information on their contribution in said programs, and offer motivation for individuals to join the programs and do well in them.

Success Criteria: The application must meet every specification, be tried and tested, stay inside spending plan, and be finished on time.

Approach:
Identify project team members
Build a reasonable work breakdown structure, scope statement, and Gantt Chart enumerating the work required to finish the Recreation and Wellness Intranet application.

Determine the project requirements
Develop the project
Test the project
Promote the application
Roll out application
Roles and Responsibilities
Name and Signature Role Position Contact Information
Dan Marino
Dan Marino Sponsor CEO [email protected]
Charles Barnes
Charles Barnes Project Manager Manager [email protected]
Jerry Rice
Jerry Rice Team Member Testing Expert [email protected]
Barry Sanders
Barry Sanders Team Member Programmer [email protected]
Deion Sanders
Deion Sanders Team Member Programmer [email protected]
Comments: (Handwritten or typed comments from above stakeholders, if applicable)
“I need to be vigorously associated with this project. It is vital to our organization’s prosperity and I anticipate that everyone will help influence it to succeed.” ——Dan Marino

Project Scope Management Task 1 (Scope Statement)
Scope Statement (Version 1)
Project Title: Recreation and Wellness Intranet Project
Date: October 30th, 2018Prepared by: Charles Barnes
Project Justification: Manage Your Health, Inc. (MYH) provides an assortment of healthcare services all over the globe. MYH has more than 20,000 full-time workers and more than 5,000 part-time workers. As of late, MYH refreshed its strategic plan and is getting ready to actualize the Recreation and Wellness Intranet Project that will enable workers to enhance their wellbeing, by means of the present intranet site. The project will take six months to finish, with a financial plan of $200,000. This application will help enhance worker wellbeing inside one year of its rollout with the goal that lower medical coverage premiums can be arranged, giving a net savings of at least $30 per full-time employee every year for the next four years.

Product Characteristics and Requirements:
Templates and Tools: The application will enable employees to register for organization supported recreational programs and wellbeing classes and programs, track information on their association in these recreational and wellbeing programs and offer motivation for individuals to join these programs and do well in them.

Employee interaction: Employees will be urged to utilize the application by offering motivation for their association.
Links: Links to external sites will be tested weekly. If broken, the links will be repaired or removed within three days.

Security: The intranet site will provide many different levels of security. All internal employees will have access to the entire intranet site after entering their login information to access the main, corporate intranet.

Search: The intranet site must have a search feature included, so users can search for keywords with quick results.

The intranet site must be accessible for use with an approved Internet browser. Users must also have suitable application software to open the tools and templates mentioned above.

The intranet site must be accessible 24 hours a day, 7 days a week, with 2 hours each week set aside for routine upkeep and other intermittent maintenance.

Product User Acceptance Criteria:
Project meets all specifications
Project is tried and tested
Project completed by projected date of April 30th, 2018
Staying inside our allocated spending plan of $200,000
Summary of Project Deliverables
Project management-related deliverables: business case, charter, team contract, scope statement, work breakdown structure (WBS), schedule, cost baseline, status reports, final project presentation, final project report, lessons-learned report, and any additional supporting documents required to manage the project.

Product-related deliverables: research reports, design documents, software code, hardware, etc.

Survey: A survey will be created and have employee input to assess the application’s user-friendliness.

Links: The intranet site will include many links and brief descriptions for several useful sites. The links will be categorized into meaningful classifications.

Articles: The intranet site will include many useful health improvement articles for employees to reference and use.

User requests feature: The intranet site will include an application to ask for and process requests from users.

Promotion: A plan for promoting the intranet site internally and externally will describe various approaches for soliciting inputs during design. The promotion plan will also announce the availability of the new intranet site.

Project Scope Management Task 2 (WBS)
Work Breakdown Structure (WBS)
October 30th, 2018
Project Name: Recreation and Wellness Intranet Project
Initiating
1.1 Identify key stakeholders
1.2 Prepare project charter
1.3 Hold project kick-off meeting
Planning
2.1 Hold team planning meeting
2.2 Prepare team contract
2.3 Prepare scope statement
2.4 Prepare WBS
Prepare schedule and cost baseline
Determine task resources
Determine task durations
Determine task dependencies
Create draft Gannt chart
Review and finalize Gantt chart
Identify, discuss, and prioritize risks
Executing
Survey
User inputs
Intranet site content
3.3.1 Templates and Tools
3.3.2 Articles
3.3.3 Links
3.3.4 User requests feature
Intranet site design
Intranet site construction
Intranet site testing
Intranet site promotion
Intranet site roll-out
Project benefits measurement
Monitoring and Controlling
Progress reports
Closing
5.1 Prepare final project report
5.2 Prepare final project presentation
5.3 Lessons Learned

Project Scope Management Task 3 (Gantt Chart)
Task Mode Task Name Duration Start Finish Predecessors Resource Names
Research and Wellness Intranet Project Tue 10/30/18 Auto Scheduled Initiating Tue 10/30/18 Manual Identify key stakeholders Manual Prepare project charter Manual Hold Project kick-off meeting Auto Scheduled Planning Tue 10/30/18 Manual Hold team planning meeting Manual Prepare scope statement Manual Prepare WBS Auto Scheduled Prepare schedule and cost baseline Tue 10/30/18 Manual Determine task resources Manual Determine task durations Manual Determine task dependencies Manual Create draft Gantt chart Manual Identify, discuss, and prioritize tasks Auto Scheduled Executing Tue 10/30/18 Manual Survey Manual User inputs Auto Scheduled Intranet site content Tue 10/30/18 Manual Templates and tools Manual Articles Manual Links Manual Ask the experts Manual User request feature Manual Intranet site design Manual Intranet site construction Manual Intranet site testing Manual Intranet site promotion Manual Intranet site roll-out Manual Project benefits measurement Auto Scheduled Monitoring and controlling Tue 10/30/18 Manual Progress reports Auto Scheduled Closing Tue 10/30/18 Manual Prepare final project report Manual Prepare final project presentation Manual Lessons learned